This Week in Freeway Closures

Long Beach prepares for the year-long closure of the 405/22/ 7th Street connector, and intermittent nighttime lane closures continue along the 405.

  • There will be extended lane closures of the eastbound Garden Grove Freeway (22) to the southbound San Diego Freeway (405) connector Saturday from 5 a.m. until 10 a.m.  The connector will be accessible between 5 a.m. and 10 a.m., but the lanes will be reduced. 
  • The southbound San Gabriel Freeway (605) to the southbound 405 connector will undergo an extended lane closure on Sunday, from 5 a.m. to 10 a.m.  The connector will be accessible between 5 a.m. and 10 a.m., but the lanes will be reduced. 
  • Median barrier removal in the center of the 405 will resume this week. Night work may be disruptive to the neighboring community due to equipment noise and back-up alarms. 
  • The Northbound 405 / westbound 22 / 7th Street Connector will close for 12 months beginning on Monday, April 18 at 10 p.m.  The connector will remain closed until April 2012.
  • The City of Long Beach has begun implementing Studebaker Road, Palo Verde Avenue and other mitigation measures in preparation of the upcoming northbound 405 / westbound SR-22 / 7th Street connector closure.  Signals along the 7th Street detour routes will be modified to facilitate optimal traffic flow.
  • Vegetation removal is postponed along the 405 / 605 interchange and adjacent to the community of Rossmoor.  Removal activities will resume sometime in the next few weeks.  Night work may be disruptive to the neighboring community due to equipment noise and back-up alarms.